Stage Set Design & Construction Schedule
Prepared by Don Puderbaugh
as of November 19, 2003
SET CONSTRUCTION (ARCHITECTURE):
- Establish Floor Plan of Set 13 - 18 Oct
- Provide Inventory List of Existing Flats and Props 27 Oct - 1 Nov
- Develop Elevation & Perspective Views of Set 22 Oct - 8 Nov
- Complete and Approve Set Design 8-Nov
- Identify Basic Flats on Plan 27 Oct - 1 Nov
- Identify Special Flats and Props: 27 Oct - 1 Nov
- Cracks
- Archway to Bar
- Window Alcove (Step, Bench, Window)
- Fireplace
- Niche at Lamp & Chair
- Design Special Flats and Props 24 - 28 Nov
- Obtain Construction Materials and Paints 26 Nov - 5 Dec
- Test Crack Concept(s) 10 - 12 Dec
- Construct Special Flats and Props 10 - 17 Dec
- Paint Special Flats and Props 15 - 19 Dec
- Construct Necessary New Basic Flats 17 - 22 Dec
- Paint Remaining Flats and Props 10 - 24 Dec
- Assemble All Flats and Props on Stage 10 Dec - 24 Dec
SET FURNITURE AND DECOR:
- Identify and List All Furniture and Décor 27 Oct - 5 Nov
- Identify Source of Each Item of F & D 3 - 18 Nov
- Obtain All Items of F & D 13 Nov - 6 Dec
- Modify Items as Required (Paint, Fabric, etc.) 1 - 18 Dec
- Install All Items of F & D on Stage 20-Dec
SET COMPLETION:
- Coordinate with Other Crews and Cast 22 - 24 Dec
- Test and Revise as Necessary 26 - 27 Dec
- Complete Total Set (Finishing Touches) 22 - 31 Dec
- Maintain Set and Props through Performances 5 - 12 Jan
- Remove Set from Stage 13-Jan
- Return Loaned Items to Owners 14 - 17 Jan
TEAM MEETINGS: 24 Oct - Fri
8 Nov - Sat
22 Nov - Sat
5 Dec - Fri
20 Dec - Sat